postheadericon Natura Design S.L. update for Playa Blanca Villa Construction Project

The villas are now ready for the external rendering and the internal plastering to begin. We have finished building the internal walls and fitted the timber pre-frames for the internal doors.

internal block work  pre frames for the plasterer  Timber frames

The roofs have been rendered and water proofed with a fine fiberglass mesh and rubber paint,

painting the roof  painting  ready for the final coat

We have started to put on the first coat of plaster to pad out the walls, we will then apply a final top coat to give us the desired finish.

internal plastering  first coat of plaster  external rendering

We apply a yellow resin to the concrete columns, this helps the render to stick to the smoother surfaces.

Natura Design  rendering  Playa Blanca villa construction update.